Campus Parking Update

TO: Campus Community

FR: Neil Markley, Associate Vice President for Administration and Finance

RE: Campus Parking Update

Welcome to the fall semester. As is the case in the first week of any semester, parking in your preferred lot may be difficult. This semester we have an added challenge — the ongoing construction work related to the campus solar installation in parking lot F.

While we understand this is not ideal, please be aware of the following:

  • Parking lots L, M, N and O are available with plenty of parking spaces. These lots are surprisingly convenient to the campus core.
  • Construction in lot F is expected to be completed in phases beginning at the end of this month. See the schedule below.
    • Lot F Phase 2A: Projected to open by August 31
    • Lot F Phase 2B: Projected to open by September 25
    • Lot F Phase 2C: Projected to open by October 12

Future Construction Activity

  • Lot J: December 18, 2023 - January 29, 2024 (weather permitting)
  • Lot R7: January 29, 2024 - March 11, 2024 (weather permitting)
  • Lot R6: March 11, 2024 - April 22, 2024 (weather permitting)

Thank you for your patience and understanding as we make good on our climate pledge and the resulting additional benefit of covered parking in our most popular lots.