This summer we are making repairs to several asphalt pedestrian pathways on campus. The repair work will be conducted in two phases:
May 22 - 24
- East side of the Recreation Center and Student Center.
Area 2
May 26 - June 9
- Gymnasium (P.E. Building) to Salazar Hall
- Salazar Hall to the Wine Spectator Learning Center
- Gymnasium (P.E. Building) to Stevenson Hall
- West side of the Gymnasium (P.E. Building) and Fieldhouse
- South of International Hall
Please consider alternate pedestrian pathways during these times to reach your desired destination.