REVISED: Solar array and battery construction schedule
TO: Campus Community
FR: J. Dana Twedell, Associate Vice President, Facilities Management
RE: REVISED Solar array and battery construction schedule
The construction schedule for our elevated steel solar structure has begun and continues through November 22, 2023.
Construction is set up in a phased approach, beginning with parking lots E and F, followed by Lot J, then Lot R7, and ending with Lot R6. Please reference the site plan and schedule below:
See a larger PDF version of this map.
Construction Schedule |
Phase |
Location |
May 30 - August 4 |
1 |
Parking Lot E |
May 30 - August 4 |
2A |
Parking Lot F |
May 30 - August 18 |
2B |
Parking Lot F |
May 30 - September 8 |
2C |
Parking Lot F |
September 11 - September 29 |
3 |
Parking Lot J |
October 2 - October 27 |
4 |
Parking Lot R7 |
October 20 - November 22 |
5 |
Parking Lot R6 |
During each phase of construction, each parking lot will be fenced off and restricted from access. We will have sufficient parking available in the adjacent parking lots during each construction phase. For current parking closures, and future projects on campus, you may refer to the Division of Administration and Finance calendar.
Thank you for your support and patience as we create a more sustainable SSU.
If you have any questions, please contact Dana Twedell, twedell@sonoma.edu.