REVISED Solar Canopy Array Project Construction Schedule

TO: Campus Community
FR: J. Dana Twedell, Associate Vice President, Facilities Management
RE: REVISED Solar Canopy Array Project Construction Schedule

The elevated steel solar array construction schedule has been adjusted. Below is a new tentative revised construction schedule. Parking lots during construction are not accessible for parking.
 

Construction Schedule

Phase

Location

May 30 – Aug. 9

1

Parking Lot E

May 30 – Aug. 21

2A

Parking Lot F

May 30 – Sept. 19

2B

Parking Lot F

May 30 – Oct. 4

2C

Parking Lot F

Tentative start Dec. 2023

3

Parking Lot J

TBD

4

Parking Lot R7

TBD

5

Parking Lot R6

 

 
We understand this delay will impact our 2023 residential community fall Move-In for students who will be living in the Beaujolais and Tuscany Villages. During the month of August, parking for the residents of Beaujolais and Tuscany will be impacted by the construction of phase 2A (see map below for phase location). It’s recommended that staff, faculty and students not residing in Beaujolais and Tuscany consider parking in alternate lots to allow the residences sufficient parking close to home. Even with these closures, we have sufficient parking available on campus.

During each phase of construction, each parking lot will be fenced off, and access restricted. Sufficient parking is available in the adjacent parking lots during each construction phase (Parking lots E, G, H, J, L, M, N and O). Please see the campus map below for parking lot locations.

If the schedule shifts, we will notify the campus of the change and impact. We apologize for any inconvenience this may cause. We thank you in advance for your support in this effort. For current parking closures and future projects on campus, you may refer to the Division of Administration and Finance calendar.

Thank you for your support and patience as we create a more sustainable SSU.